Underground cabling: Ginger HPC as an advocate for soil and construction companies

The urgency of grid expansion to drive the energy transition has become particularly evident due to the Ukraine war. While protests from residents regularly attract media attention, the potentially harmful impacts on the soil itself often go unnoticed. GINGER HPC AG, however, keeps a close eye on the effects on soil, its functions, and its properties. As a result, GINGER HPC represents the interests of future land users, such as farmers, while also providing technical assurance to construction companies on site.

The GINGER HPC team from the Leer branch supports TenneT TSO GmbH in its project to construct a new high-voltage transmission line between the substations in Ganderkesee and St. Hülfe bei Diepholz. Electricity generated in the north is to be made available in southern and western Germany, contributing to the energy transition.

The new 380 kV line is approximately 61 kilometers long, around 13 kilometers of which consist of three underground cable sections (Fig. 1).

This is where we come in:

  • Through our involvement in soil-related construction supervision, we are continuously present on site, ensuring that all soil-related aspects are properly considered.
  • Throughout the entire project duration, we have carried out numerous on-site investigations required as part of the construction process.
  • Our scope of services includes, for example, soil investigations in accordance with the guidelines of the Federal Soil Protection Act (BBodSchG) and LAGA, determination of grain size distribution, thermal conductivity measurements, soil water tension measurements using tensiometers, sampling with core cutters, and the installation of groundwater monitoring wells.
  • With these investigations (e.g., core cutter samples), we verify, among other things, whether reinstalled soils have been properly compacted.
  • In coordination with the client, we also handle communication with the responsible soil protection authority. In most cases, obtaining a building permit includes the requirement for soil-related construction supervision. Our qualified soil experts support the client from planning through implementation to final land restoration.
Auftraggeber:
TenneT TSO GmbH
Projektbeginn:
Gen 2023
Projektdauer:
ongoing
Projektstandort:
Ganderkesee – St. Hülfe (Diepholz), Niedersachsen, Germany
Fläche:
61 km (of which 13 km are underground cable sections)

The goal of soil science-based construction supervision is the complete reclamation of the land used, so that it appears as if no construction work had taken place. This goes hand in hand with preventing harmful changes to the soil. Losses in crop yield for landowners can be significantly reduced through construction methods that minimize soil disturbance.

Of course, this involves not only the appearance of the mostly agricultural land after construction is complete, but also the proper restoration of soil functions as grassland or cropland, as well as the creation of an optimal environment for the cable route. During construction, strict separation of soil types is therefore ensured. In addition, the paths used by construction machinery are specifically protected against compaction damage.

To lay the underground cables, the topsoil is first carefully removed and deposited in a pile running parallel to the cable trench, to the side of the construction site. The underlying subsoil layers are then excavated separately and also stored to the side, but in separate piles. In the next step, the welded-together conduit pipes are laid along the cable trench, and the trench is backfilled while maintaining the original sequence and thickness of the soil layers. During backfilling, the soil is screened using a screening machine to remove large stones that could have damaged the conduit pipes (Fig. 2).

After the cable trench has been backfilled, the power cables are unrolled from a cable drum and pulled into the conduit. The ends of the custom-cut cables are joined in a joint pit (Fig. 3), creating an uninterrupted power line.

Sometimes, as a soil science construction supervisor, one must stand in the way of the schedule and make decisions to protect the soil that lead to the displeasure of the construction companies. Nevertheless, we remain steadfast and defend the soil, because every construction project carries the risk of harmful soil changes, such as harmful compaction.

During longer construction projects, such as the one in Ganderkesee, a variety of weather conditions—both favorable and unfavorable—are encountered over the course of the project. To preserve natural soil functions despite adverse conditions, the risk of harmful compaction can be significantly reduced through planning measures taken before construction begins and through consultation during the project. The preservation of natural soil functions is the top priority.

The soil must also be protected during construction work. This is achieved by training equipment operators on-site and by selecting the right equipment. People on the construction site are instructed by the soil science construction supervisor and made aware of the importance of treating the soil with care. In this way, much damage can be prevented in advance. If problems do arise, practical solutions are found and implemented on-site. This helps reduce follow-up costs for reclamation measures.

We therefore act, on the one hand, as advocates for farmers and other landowners, and, on the other hand, in an advisory capacity for the construction companies working on-site.

Erdverkabelung: Ginger HPC als Advokat des Bodens und der bauausführenden Unternehmen

Die Dringlichkeit des Netzausbaus, um die Energiewende voranzubringen, ist auch durch den Ukraine-Krieg offensichtlich geworden. Proteste von Anwohner:innen erregen regelmäßig…
Learn more

Underground cabling: Ginger HPC as an advocate for soil and construction companies

The urgency of grid expansion to drive the energy transition has become particularly evident due to the Ukraine war. While…
Learn more

Erdverkabelung: Ginger HPC als Advokat des Bodens und der bauausführenden Unternehmen

Die Dringlichkeit des Netzausbaus, um die Energiewende voranzubringen, ist auch durch den Ukraine-Krieg offensichtlich geworden. Proteste von Anwohner:innen erregen regelmäßig…
Learn more

Bauen in doppelter Wasserlage

Kita am Baakenhafen Die Hamburger HafenCity ist eines der eindrucksvollsten Bauprojekte in Hamburg: Entlang der Elbe entsteht hier seit 2001…
Learn more

Building between two water levels

Hamburg’s HafenCity is one of the most impressive urban development projects in the city: since 2001, an entirely new district…
Learn more

Bauen in doppelter Wasserlage

Die Hamburger HafenCity ist eines der eindrucksvollsten Bauprojekte in Hamburg: Entlang der Elbe entsteht hier seit 2001 ein komplett neuer…
Learn more

Dem Wasser gefolgt: Generalentwässerungsplan für Meerbusch

Neues Entwässerungskonzept für Meerbusch-Strümp Der Auftrag war klar: Der inzwischen 20 Jahre alte Generalentwässerungsplan sollte aktualisiert werden. Neu waren nicht…
Learn more

Following the water: General drainage plan for Meerbusch

The task was clear: the general drainage plan, now 20 years old, needed to be updated. Not only were there…
Learn more

Dem Wasser gefolgt: Generalentwässerungsplan für Meerbusch

Der Auftrag war klar: Der inzwischen 20 Jahre alte Generalentwässerungsplan sollte aktualisiert werden. Neu waren nicht nur diverse Baumaßnahmen oder…
Learn more

In-situ: Wie von Zauberhand entfernt

Biologisch-chemische In-situ-Sanierung von LHKW Leichtflüchtige halogenierte Kohlenwasserstoffe sind nur schwer aus dem Boden zu entfernen. Bernadette Bohnert und ihr Team…
Learn more

In-situ: Removed as if by magic

Volatile halogenated hydrocarbons are difficult to remove from soil. Bernadette Bohnert and her team used an innovative method for contaminant…
Learn more

In-situ: Wie von Zauberhand entfernt

Leichtflüchtige halogenierte Kohlenwasserstoffe sind nur schwer aus dem Boden zu entfernen. Bernadette Bohnert und ihr Team nutzten für die Schadstoffsanierung…
Learn more

I Vostri vantaggi con GINGER HPC

Più di 75 anni di esperienza

Dal 1948 GINGER HPC unisce competenza e precisione in progetti ambientali e ingegneristici per soluzioni affidabili che durano nel tempo.

Forte rete internazionale

Con sedi in tutta Europa come parte del gruppo Ginger e membro fondatore della Inogen Alliance uniamo prospettive globali a competenze locali in ogni progetto.

Eccellente sostenibilità

Dalle certificazioni internazionali ai premi di settore i nostri riconoscimenti rappresentano precisione ingegneristica standard elevati e un continuo impegno per l’innovazione.

Unsere Leistungsbereiche

No child pages found for the selected parent.

Gestalten Sie schon heute die Welt von morgen mit

Haben Sie Lust auf Kolleg:innen in Ihrer Arbeitsumgebung, die mit Leidenschaft und hoher Qualifikation in Projekten arbeiten?

Sie mögen es, langfristige Kund:innen-Partnerschaften aufzubauen und sich in immer neuen Projekten weiterzuentwickeln? Sie sind gerne dazu bereit, Ihren Kund:innen den bestmöglichen Service zu bieten?

Dann sollten wir uns kennenlernen, denn wir suchen Sie zur Verstärkung unseres GINGER HPC-Teams.

Jetzt bewerben
Consenso ai cookie con Real Cookie Banner