Neu verlegte blaue Wasserleitungen mit Absperrarmaturen in einer Baugrube; die Rohre liegen im Kiesbett, darüber eine freigelegte Erdschicht und Baumaschinen im Hintergrund.

Back on Track: New Pipelines for Clean Water

Rehabilitation of the Wastewater Systems in Spittal/Drau

60 years that is roughly the service life of sewer systems. Why does that matter? When wastewater no longer flows properly, it can escape from the system and contaminants may enter the groundwater. This can have serious consequences for both people and the environment. To prevent this, the municipality of Spittal/Drau commissioned a comprehensive rehabilitation of its wastewater systems.

Precise preliminary work – the key to success
Under the direction of Ingenieurbüro Kronawetter GmbH (now HPC IBK), the entire combined sewer system was first examined, including pumping stations, combined sewer overflow structures and retention basins. This involved not only inspecting the existing sewer network but also measuring flow and precipitation volumes as well as assessing the impact on groundwater and surface water.

The result: significant hydraulic deficiencies had to be addressed immediately. Based on the hydraulic and structural assessment of the inspected sewers, the ecological situation and the possible future development of the system, a comprehensive rehabilitation plan was developed and implemented over a period of almost three years.

Implementation – Following the Path of the Sewers

Leaking and outdated sewer systems were rehabilitated using two different methods. In some sections, underground repairs were carried out using trenchless lining techniques (inliner method), which allow renewal within the existing pipes. In other areas, trenches were excavated and the pipes were completely replaced.

While these tasks themselves posed no difficulty for our experienced specialists, the team faced a very different challenge.

Clean into the Future

After only three years of planning and implementation, parts of the sewer system in Spittal/Drau are now operating like new again. The system has been upgraded to the latest state of the art and is therefore more sustainable than ever before.

No wastewater can enter the groundwater anymore, and in the long term the municipality will benefit from reduced operating and maintenance costs. Once again, our team has demonstrated that we combine technical expertise with a strong focus on sustainability.

The major challenge in this project lay in the extremely limited space and accessibility on site. In the western and eastern construction areas, the new daycare center building directly borders neighboring buildings that are still under construction. To the north and south, the excavation pit directly adjoins public spaces: on one side there is a tartan running track where neither construction vehicles can drive nor building materials can be stored. On the other side, the only access to the construction site is a one-way street with adjacent cycling and pedestrian paths. This means that extensive work, such as excavation, had to be organized under one-way traffic conditions.

This created major logistical challenges, not least when installing the water treatment plant required for groundwater lowering. Since there was very little space available around the excavation pit, the plant was installed 250 meters away on a plot of land where construction had not yet begun. A complex task in whose planning and implementation GINGER HPC was involved. In doing so, we made a significant contribution to preventing contamination of the Elbe River and the groundwater.

In the meantime, buoyancy protection for the new building is ensured by its own weight and additional structural load. As a result, the groundwater management system has been successfully completed and dismantled.

And Now? Moving into the Future with Sustainability

The space along the sides of the excavation pit is available for backfilling. It is planned to fill the southern shoring area, under the professional supervision of GINGER HPC, with flowable fill (liquid soil) up to 1.5 m below ground level. The sandy backfill to be placed above will be flushed in with water. During this process, the timber lagging will be gradually removed.

Finally, the public areas such as roads, pedestrian and cycle paths, as well as infrastructure including sewer lines for wastewater and stormwater, will be inspected through comprehensive elevation surveys, compaction tests and CCTV inspections of the pipelines. GingerHPC plans and initiates the required evidentiary safeguarding measures, carries out some of them directly, and evaluates the results.

Auftraggeber:
Municipality of Spittal an der Drau
Projektdauer:
3 Years
Projektstandort:
Austria

The project remains an exciting one for GINGER HPC. Following the successful excavation of the construction pit, structural construction works are now in full progress. Our team of experienced engineers continues to support the project with expert advice on geotechnical and environmental matters.

One of the next tasks will be the dismantling of the excavation support system, which consists of a braced Berlin-type shoring system on the north side and a double-anchored Essen-type shoring system on the south side. Extremely tight space conditions in the area alongside the excavation pit—locally only about 10 cm between the new building and the soldier pile shoring—pose particular challenges, especially on the south side, when backfilling the approximately 5-metre-deep space.

Erdverkabelung: Ginger HPC als Advokat des Bodens und der bauausführenden Unternehmen

Die Dringlichkeit des Netzausbaus, um die Energiewende voranzubringen, ist auch durch den Ukraine-Krieg offensichtlich geworden. Proteste von Anwohner:innen erregen regelmäßig…
Learn more

Underground cabling: Ginger HPC as an advocate for soil and construction companies

The urgency of grid expansion to drive the energy transition has become particularly evident due to the Ukraine war. While…
Learn more

Erdverkabelung: Ginger HPC als Advokat des Bodens und der bauausführenden Unternehmen

Die Dringlichkeit des Netzausbaus, um die Energiewende voranzubringen, ist auch durch den Ukraine-Krieg offensichtlich geworden. Proteste von Anwohner:innen erregen regelmäßig…
Learn more

Bauen in doppelter Wasserlage

Kita am Baakenhafen Die Hamburger HafenCity ist eines der eindrucksvollsten Bauprojekte in Hamburg: Entlang der Elbe entsteht hier seit 2001…
Learn more

Building between two water levels

Hamburg’s HafenCity is one of the most impressive urban development projects in the city: since 2001, an entirely new district…
Learn more

Bauen in doppelter Wasserlage

Die Hamburger HafenCity ist eines der eindrucksvollsten Bauprojekte in Hamburg: Entlang der Elbe entsteht hier seit 2001 ein komplett neuer…
Learn more

Dem Wasser gefolgt: Generalentwässerungsplan für Meerbusch

Neues Entwässerungskonzept für Meerbusch-Strümp Der Auftrag war klar: Der inzwischen 20 Jahre alte Generalentwässerungsplan sollte aktualisiert werden. Neu waren nicht…
Learn more

Following the water: General drainage plan for Meerbusch

The task was clear: the general drainage plan, now 20 years old, needed to be updated. Not only were there…
Learn more

Dem Wasser gefolgt: Generalentwässerungsplan für Meerbusch

Der Auftrag war klar: Der inzwischen 20 Jahre alte Generalentwässerungsplan sollte aktualisiert werden. Neu waren nicht nur diverse Baumaßnahmen oder…
Learn more

In-situ: Wie von Zauberhand entfernt

Biologisch-chemische In-situ-Sanierung von LHKW Leichtflüchtige halogenierte Kohlenwasserstoffe sind nur schwer aus dem Boden zu entfernen. Bernadette Bohnert und ihr Team…
Learn more

In-situ: Removed as if by magic

Volatile halogenated hydrocarbons are difficult to remove from soil. Bernadette Bohnert and her team used an innovative method for contaminant…
Learn more

In-situ: Wie von Zauberhand entfernt

Leichtflüchtige halogenierte Kohlenwasserstoffe sind nur schwer aus dem Boden zu entfernen. Bernadette Bohnert und ihr Team nutzten für die Schadstoffsanierung…
Learn more

I Vostri vantaggi con GINGER HPC

Più di 75 anni di esperienza

Dal 1948 GINGER HPC unisce competenza e precisione in progetti ambientali e ingegneristici per soluzioni affidabili che durano nel tempo.

Forte rete internazionale

Con sedi in tutta Europa come parte del gruppo Ginger e membro fondatore della Inogen Alliance uniamo prospettive globali a competenze locali in ogni progetto.

Eccellente sostenibilità

Dalle certificazioni internazionali ai premi di settore i nostri riconoscimenti rappresentano precisione ingegneristica standard elevati e un continuo impegno per l’innovazione.

Unsere Leistungsbereiche

No child pages found for the selected parent.

Gestalten Sie schon heute die Welt von morgen mit

Haben Sie Lust auf Kolleg:innen in Ihrer Arbeitsumgebung, die mit Leidenschaft und hoher Qualifikation in Projekten arbeiten?

Sie mögen es, langfristige Kund:innen-Partnerschaften aufzubauen und sich in immer neuen Projekten weiterzuentwickeln? Sie sind gerne dazu bereit, Ihren Kund:innen den bestmöglichen Service zu bieten?

Dann sollten wir uns kennenlernen, denn wir suchen Sie zur Verstärkung unseres GINGER HPC-Teams.

Jetzt bewerben
Consenso ai cookie con Real Cookie Banner